    Stages of Construction


    Kitchen Remodel - Sequence of Events

    Phase 1: Preparing Space

    Preparation & Demolition:
  • Contractor to schedule cabinet demolition, electrician, plumber, drywaller & painter
  • Empty cabinets of cookware, pots, pans, dishes, etc.
  • Protect existing floor if not replacing it (red rosin paper or similar)
  • Dust barriers at interior door openings (duct tape plastic over openings)
  • Demolition of existing cabinetry and appliances (drywall ceiling, walls & flooring)
  • Remove demolition debris from jobsite or into jobsite dumpster
  • Rough Ins:
  • Relocate existing or new construction if necessary (pony walls, skylights, garden window)
  • Relocate electrical rough-ins for 110V outlets, appliances & lighting
  • New electrical rough-ins if necessary (220V for oven, new microwave circuit, etc.)
  • Relocate mechanical rough-ins (H20 & waste line for sink, HVAC, etc.)
  • Plumber to locate sink drain minimum 14 clearance off finished floor on German cabinetry
  • New mechanical rough-ins if necessary (new gas or water lines to island, etc.)
  • Install & wire new ceiling lighting & under cabinet lighting
  • Insulation in exterior walls & ceiling if necessary
  • Drywall, Paint & Flooring:
  • Apply new drywall & 3 coats of taping compound & drywall patch as needed
  • Prime coat drywall, one coat of paint (optional)
  • Install new flooring before cabinet installation (vinyl flooring after cabinet installation)
  • Scheduling of Trades:
  • Schedule cabinet installation with project assistant (three to four weeks notice)
  • Schedule granite fabricator for measuring or tile installer at this time
  • Schedule sinks & appliances delivered to jobsite before cabinet installation
  • Phase 2: Installation of Cabinets

  • Install cabinet bases, uppers & tall cabinetry
  • Install cabinet fillers, overlays, scribe moulding, crown moulding
  • Install plywood roughtops and make appliance cutouts
  • Jobsite inspection & walk through to include GC, designer & client/owner
  • Review Sequence of Events list again with client
  • Remove cabinet wrapping debris from jobsite or into jobsite dumpster
  • Phase 3: Countertop & Appliance Installation
  • Schedule appliance installation at this time
  • Granite measure & fabrication (approximately 7-10 working days)
  • Tile, grout & seal (approximately 5-7 working days)
  • Installation of appliances & sinks
  • Electrical & Mechanical hook-ups (plumbing, 110V outlets & switches, under cabinet lights, etc.)
  • Phase 4: Final Installation
  • Installation of light valance (after countertops & backsplash installation)
  • Installation of appliance panels (after appliances are installed)
  • Installation of toekick moulding
  • Detail cabinetry (clean out cabinet interiors, adjust doors & drawers, fine tune cabinetry)
  • Remove remaining cabinet debris from jobsite
  • Finals jobsite inspection to include GC, designer & client/owner
  • The Kitchen Factory looks forward to creating a functional kitchen that is a true expression of your unique taste.



  • The Kitchen Factory , 12326 Ventura Boulevard, Studio City, California 91604

     

    Since 1988 serving Beverly Hills, Pacific Palisades, West Los Angeles, Encino, Santa Monica, Malibu, West Hollywood, Brentwood, Bel Air, Studio City, Sherman Oaks, Tarzana, Woodland Hills, Toluca Lake, Burbank, Pasadena, San Marino, Glendale, Calabasas, Woodland Hills, Westlake Village, Rancho Palos Verdes, and Los Angeles.

     
    Home     |      Design Portfolio     |      What's Fresh     |      Manufacturers
    About Us     |      Services     |      Contact

    All content 2010 The Kitchen Factory. All rights reserved. All trademarks, product names, and company names or logos cited herein are the property of their respective owners.